Google Summer of Code 2023 Weekly Status Reports

What progress have you made this week?

  • Consistency of the feature OnCallDoctors for ECEB from NeoReo , worked on implementation of this functionality data fetched for new trackedEntity which is used in NeoReo application
  • Related Issue
  • Worked on improving the workflow of the current figma designs for ECEB application
  • ECEB Enhancements Figma

What do I plan to do next week?

  • Work on suitable model for OnCallDoctor and display list on frontend
  • Work on design for eceb and underlying issues of application

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

  • Implemented the ToDo functionality to add, update and delete the ToDo.
  • Related Issue -: Related Merge Request
  • Started the work on the functionality to create a graph of infants.

What do I plan to do next week?

  • Complete the functionality to create graphs for the infant data.
  • Start work on sending notifications to the user.

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What do I plan to do next week?

  • Create a dashboard UI for sent invitations.
  • Add Validation and response messages to the forms.

Have you had any blockers or issues that are impeding your project?

None

What progress have you made this week?

  1. Discussed with the mentors more about the color coding of the vitals

  2. Implemented the changes in the UI of HomePage based on Khushboo’s changes in the design

  3. Implemented the color coding in choose vitals screen

What do I plan to do next week?

  1. Implement the baby’s list screen UI in Flutter
  2. Implement the More Options Screen UI in Flutter
  3. Implement any changes made on the previous screens for the color coding

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What I plan to do next week?

  • Complete Mammography breast cancer model integration to the AI Model Service
  • Meet with mentor for feedback, guidance and to move forward

Have you had any blockers or issues that are impeding your project?

  • None

What progress have you made this week?

  • Implementation of On Call feature left over work and issues from NeoReo to ECEB was done
  • Related Issue
  • Refining current figma designs for ECEB application still waiting for approvals for implementations
  • ECEB Enhancements Figma

What do I plan to do next week?

  • Start Implementation of an approved iteration of design from mentors
  • Work on implementing the feature for new organizations options to user to choose from by fetching api data and implementation of new bloc for organizations

Have you had any blockers or issues that are impeding your project?

  • Approval on design is major blocker

What progress have you made this week?

  1. Implemented More Options Screen UI
  2. Implemented Babies List Screen UI

What do I plan to do next week?

  1. Implement the Notification Screen
  2. Implement the Add/Update baby details screen

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What do I plan to do next week?

  • Enhancements in the graphs.
  • Start work on implementing the notification functionality.

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What I plan to do next week?

  • Currently integrated VGG16 mammography model. Integrate the RSNA kaggle competition model.
  • Meet with mentor for feedback, guidance and to move forward

Have you had any blockers or issues that are impeding your project?

  • None

What progress have you made this week?

What do I plan to do next week?

  • Finalise the Invitation Module and user creation
  • Implement the reviews and suggestion from mentor

Have you had any blockers or issues that are impeding your project?

Handling json based api response with Inertia

What progress have you made this week?

What do I plan to do next week?

  • Implement the functionality fetch all record and fetch 24 hour summary
  • Start work for approved design iteration

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What do I plan to do next week?

  • Start working to integrate communication in the application.

Have you had any blockers or issues that are impeding your project?

  • No
1 Like

What progress have you made this week?

  • Had a call with my mentor to discuss reviews.
  • Optimized and updated the code with best practices as reviewed by the mentor on the last commit.
  • Created the Invitations List UI to show all the invitations sent to the user.
  • PR Link: https://github.com/LibreHealthIO/lh-ehr-laravel/pull/43

What do I plan to do next week?

  • Complete the Invitation and User module.

Have you had any blockers or issues that are impeding your project?

  • None

What progress have you made this week?

  1. Implemented Notification Screen UI
  2. Started on implementing the Add/Update baby details screen

What do I plan to do next week?

  1. Finish the Add/Update baby details screen
  2. Implement the temperature screens
  3. Decide on which training videos should be specified to care providers from this link: English Language Videos - Global Health Media Project

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

  • Discussed with mentor on MRs and upcoming tasks
  • Research and code base understanding of current top kaggle RSNA model for Mammography cancer classification
  • WIP in development and integration of RSNA model. Expect to push an MR by early next week.

What I plan to do next week?

  • Complete and push MR for updated RSNA Mammography cancer classification model
  • Code understanding and start development to connect the React OHIF framework with the Controllers

Have you had any blockers or issues that are impeding your project?

  • None

What progress have you made this week?

What do I plan to do next week?

  • Start work for approved design iteration

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What do I plan to do next week?

  • Create QR Code to register the user in the Neo Roo Program.
  • Create long pooling functionality in the chat rooms.

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What I plan to do next week?

  • Progress on React OHIF hook implementation
  • Meet with mentor

Have you had any blockers or issues that are impeding your project?

  • None

What progress have you made this week?

  1. Implemented Add/Update Baby Details Screen

  2. Implemented Temperature Chart Screen

  3. Had a very important discussion with our mentor @sunbiz about some modifications that mainly include these 2 parts:

    1. Some modifications on the temperature chart screen:

      • The chart should allow the user to zoom in on specific areas
      • The chart should have the high-temperature and low-temperature icons on any part with critically low or critically high temperatures.
      • Unit scaling when converting from Celsius to Fahrenheit and vice versa.
      • The chart should be more flexible to indicate other vitals, too.
    2. Some modifications regarding the responsiveness of the screens in general:

      • Ensuring the responsiveness of all the screens across different screen resolutions.
      • Ensuring that every screen has a working landscape view besides the portrait view.

What do I plan to do next week?

  1. Fix the above issues with the temperature chart screen
  2. Finish the Training Modules Screens (2 screens)
  3. Implement the routing of all the app
  4. Fix the above issues with the responsiveness of the screens in general

Have you had any blockers or issues that are impeding your project?

  • No

What progress have you made this week?

What do I plan to do next week?

  • Work on requested review and changes from the mentor.
  • Will work on the completion of the project.

Have you had any blockers or issues that are impeding your project?

None